Road Projects

______________________________________________________________________________

The Village of Little Chute Department of Public Works is constantly undertaking a variety of projects ranging form road construction, water and sewer replacement and storm water management. Throughout the course of the year, road project updates will be available.


Moasis Drive Detour

On Monday; August 10
th, 2020 the Village of Little Chute will begin reconstruction of the water main and replacement of effected concrete pavement.  Dorner Inc. was selected as the General Contractor and will be installing the new water main. Vinton Construction Co. will be the sub-contractor in charge of the concrete pavement replacement. During construction the Village is allowing Moasis Drive to be closed on a block by block basis for the safety of those trying to pass through the construction zone, as well as the crews working in a confined area.

The Contractor will be setting up a detour which will route truck traffic as follows:

South on Freedom Road (CTH “N”) to E. North Avenue (CTN “OO”)
East on E. North Avenue (CTN “OO”) to Buchanan Street
North on Buchanan Street to destination

For more information click here.

For map of detour click here.

Questions?
   Call (920) 423-3865.



2020 UTILITY & STREET CONSTRUCTION – HOMEWOOD COURT


Schedule: May 2020 to October 2020

Project Description:

The project scope of work includes reconstruction of approximately 1,550 centerline feet of roadway along Homewood Court from West Florida Avenue to West Florida Avenue in the Village of Little Chute.

The existing water main and storm sewer infrastructure along the project has become ineffective and or deteriorated and is in need of replacement.  The aged ductile iron water main has experienced multiple water main breaks and will be replaced with new PVC water main.  The storm sewer pipe is currently undersized for the area and is in need of upsizing.  Existing pavement condition has reached the end of its practical service life and is also in need of replacement.  Street work consists of excavation to proposed subgrade and the installation of new stone base, concrete pavement, concrete curb and gutter, driveway approaches, sidewalks, terrace restoration, and permanent signage.  The proposed typical section of Homewood Court includes 7-inches of concrete, over 8-inches of granular base material.  The new pavement will comprise of two 11-foot wide drive lanes and one 6-foot wide parking lane.

UPDATED WEEKLY SCHEDULE - (July 27th to July 31st)

HOMEWOOD COURT UTILITIES

Don Hietpas & Sons is working on Homewood Court and has completed the water, sanitary, and storm sewer utilities. Miscellaneous construction and adjustments may continue through this week. Homewood Court is an active construction site. For your safety as well as those working in the area, please avoid use when possible.   

HOMEWOOD COURT PAVING

Vinton Construction is the general contractor for the Village paving contract on Homewood Court. Vinton is anticipated to begin the excavation in preparation for concrete pavement in the middle of August. We do not have an exact start date for the excavation and grading at this time. Updates on schedule will be posted as soon as that information is available. A more detailed schedule will be provided at that time.

Traffic Impacts: Homewood Court is closed to through traffic. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Residents, business owners, and customers may access properties past “ROAD CLOSED – LOCAL TRAFFIC ONLY” signs. Parking is not permitted on the street, access for drop off and pick up are allowed. Residents should expect additional restrictions due to installation of proposed utilities.

2020 UTILITY & STREET CONSTRUCTION – CAROL LYNN DRIVE

Schedule: June 2020 to October 2020

Project Description:

The project entails reconstruction of approximately 1,670 centerline feet of roadway along Carol Lynn Drive from East Lincoln Avenue to East Wisconsin Avenue in the Village of Little Chute.

The existing water main and storm sewer infrastructure along the project has become ineffective and or deteriorated and is need of replacement.  The ductile iron water main has experienced multiple water main breaks, new PVC water main will be installed.  The storm sewer is currently undersized for the area and is need of upsizing.  The current pavement has reached the end of its service life and is need of replacement.  Street work consists of excavation to subgrade and the installation of new stone base, concrete pavement, concrete curb and gutter, driveway approaches, sidewalks, terrace restoration, and permanent signage.  The proposed typical section of Carol Lynn Drive includes 7-inches of concrete, over 8-inches of granular base material.  The new pavement will comprise of two 11-foot wide drive lanes and one 6-foot wide parking lane.

UPDATED WEEKLY SCHEDULE - (July 27th to July 31st)

CAROL LYNN DRIVE UTILITIES

Don Hietpas & Sons has completed the installation of the new water main and will be connecting resident’s water services to the new water distribution system. Hietpas will also continue the installation of the new storm sewer. Carol Lynn Drive is an active construction site. For your safety as well as those working in the area, please avoid use when possible.   

Hietpas and The Village were informed on Monday, July 6th that the United States Post Office (USPS) will no longer be delivering mail on Carol Lynn Drive as of Monday, July 6th. Mail will be held at the Post Office for residents to pick up individually; until such a time, when the USPS decides it is safe to resume mail delivery. We apologize for the inconvenience and we thank you for your cooperation in this effort.  

CAROL LYNN DRIVE PAVING

Vinton Construction is the general contractor for the Village paving contract on Carol Lynn Drive. Vinton is anticipated to begin the excavation in preparation for concrete pavement in the middle of August. We do not have an exact start date for the excavation and grading at this time. Updates on schedule will be posted as soon as that information is available. A more detailed schedule will be provided at that time.

Traffic Impacts: Carol Lynn Drive is closed to through traffic. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Residents, business owners, and customers may access properties past “ROAD CLOSED – LOCAL TRAFFIC ONLY” signs. Parking is not permitted on the street, access for drop off and pick up are allowed. Residents should expect additional restrictions due to installation of proposed utilities.


Construction Update for Warranty Work on Hayes/Wilson/Daytona



Wilson Street from Main Street to McKinley Avenue

Schedule: Current to End of May (Intermittent)

Description: Current work being completed includes street pavement patches, concrete driveway apron and sidewalk patches as well as miscellaneous landscape or turf restoration.

Project work has been substantially completed. Various Contractors may be on-site completing miscellaneous punch-list and or warranty items to bring construction to full completion. Items currently being completed or corrected are covered under the Project Warranty at no additional cost to The Village or its residents.

Traffic Impacts: Wilson Street is open to through traffic. Potential for lane restrictions and limited construction activity. Please be cautious and slow down around construction workers and equipment.

Hayes Street from Riverside Drive to Main Street

Schedule: Current to End of May (Intermittent)

Description: Current work being completed includes street pavement patches, concrete driveway apron and sidewalk patches as well as miscellaneous landscape or turf restoration.

Project work has been substantially completed. Various Contractors may be on-site completing miscellaneous punch-list and or warranty items to bring construction to full completion. Items currently being completed or corrected are covered under the Project Warranty at no additional cost to The Village or its residents.

Traffic Impacts: Hayes Street is open to through traffic. Potential for lane restrictions and limited construction activity. Please be cautious and slow down around construction workers and equipment.

Daytona Lane from North Avenue “OO” to Tampa Way

Schedule: Current to End of May (Intermittent)

Description: Current work being completed includes concrete driveway apron and sidewalk patches as well as miscellaneous landscape or turf restoration.

Project work has been substantially completed. Various Contractors may be on-site completing miscellaneous punch-list and or warranty items to bring construction to full completion. Items currently being completed or corrected are covered under the Project Warranty at no additional cost to The Village or its residents.

Traffic Impacts: Daytona Lane is open to through traffic. Potential for lane restrictions and limited construction activity. Please be cautious and slow down around construction workers and equipment.


2020 Village of Little Chute Projects

For a full description of each project click here.  Any questions regarding projects call (920) 423-3865.

              *Railroad Quiet Zones    *Moasis Drive *Vandenbroek Pond
                                             *Homewood Court              *Carol Lynn Drive

Updates:

Prior to the reconstruction of underground infrastructure and pavement on Homewood Ct, WE Energies and their subcontractor Michel’s Construction will start gas main relocation Monday, April 6, 2020. They will start on the west entrance of Homewood Ct and W. Florida Ave. It is anticipated that the main will take a week to install and gas up. At that time, they will transfer services from the old main on to the new main. All construction is planned to be completed by Friday April 24, 2020.


To bid on the 2020 utility and street reconstruction projects click the link here and enter the following quest numbers:


2020 Concrete Paving - Homewood Court and Carol Lynn Drive
Quest E-Bid  Doc # 6726167

2020 Utilities Project - Homewood Court and Carol Lynn Drive
Quest E-Bid  Doc # 6724625

2020 Railroad Quiet Zone Crossing Implementation
Quest E-Bid Doc # 6840686

2020 Water Main Reconstruction - Moasis Drive
Quest E-Bid Doc # 6840612


Bore Hole Testing

The Village will be conducting bore hole testing the week of February 3rd - 7th for our 2020 projects – Homewood Court, Carol Lynn Drive, Vandenbroek Pond and Moasis Drive. 

Bore hole testing is used to find out the structure and content of the ground / soil before construction begins.  If you have any questions call (920) 423-3865.


Public Hearing Carol Lynn Drive and Homewood Court:

           Date:                Wednesday, February 19, 2020
             Time:                6:00 p.m.
             Location:          Village Hall, Village Board Room

Click here for outline presented at Public Hearing Meeting.

Click here for frequently asked questions presented at Public Hearing Meeting.

Click here for the Preliminary Engineer's Report.


Public Informational Meeting Carol Lynn Drive and Homewood Court:

 Date:                Wednesday, January 8th, 2020
            Time:                6:00 p.m.
             Location:         Village Hall, Village Board Room

Click here for outline presented at Public Informational Meeting.

Public Informational Meeting Moasis Drive, Vandenbroek Pond, and Railroad Quiet Zones:

Date:                Wednesday, January 22, 2020
            Time:                6:00 p.m.
             Location:         Village Hall, Village Board Room

Click here for outline presented at Public Informational Meeting.


         Thank you for your patience throughout the reconstruction process!